This phased approach provided for a progressive turnover of assets to operations over time, avoiding a commissioning bottleneck in the final stages of the project, and enabling early testing of the Mine, Primary Extraction and Utilities facilities. The project has already completed five test runs of the plant, producing 1.4 million barrels of froth. The second and third trains of secondary extraction are being insulated and expected to start up in the first half of 2018, as planned. Fort Hills remains on track to reach 90 per cent capacity by the end of 2018. Suncor’s 2018 capital program will be focused on the efficient and effective ramp up at both of Suncor’s major growth projects, Fort Hills and Hebron, development of step-out offshore projects and improving the safety and reliability of the company’s operating assets. “The value of our integrated model was front and centre this quarter as strong financial re JULY 2018 | BUSINESS ELITE CANADA 7