P. 8

CONVEYANCE SYSTEM                              –Major Infrastructure Component towards the

                                                                McLoughlin Point Wastewater Treatment Plant; up

                                                                to $50 million through the Green Infrastructure Fund
        The conveyance system refers to the 'pumps and
                                                                towards the conveyance system project; and up to
        pipes' of the Wastewater Treatment Project. This
                                                                $41 million towards the Residuals Treatment Facility
        system will carry wastewater from across the core
                                                                through the P3 Canada Fund.
        area to the treatment plant, and residual solids to
        the Residuals Treatment Facility at Hartland Landfill.
                                                                The Government of British Columbia will provide up
        RECORD INVESTMENTS FOR B. C.                            to $248 million towards the three components of

                                                                the project. The Capital Regional District is providing

                                                                $316 million for the three project components and
        The Government of Canada is contributing up to
                                                                will be responsible for any additional costs.
        $120 million through the Building Canada Fund