Page 2 - Highway 15 Twinning Project
P. 2

ood news on the horizon for the 18,000         The work in Highway 15 was divided into two

                 drivers who travers Highway 15 every day in    sections. Component A was finished on October,

        GAlberta connecting the cities of Edmonton              2019 after 5 months of work. The remaining work on
        and Fort Saskatchewan.                                  Component B is scheduled to be completed in fall,

                                                                2022. To date, the North Saskatchewan river bridge

        The vital service and trade corridor is expanding       with an underslung pedestrian bridge is 65 per cent
        from one lane of traffic in each direction with         complete, Road construction is at 50 per cent, and

        increased lanes, a new parallel bridge and a            the sewer and retaining walls are both nearly done.
        pedestrian bridge.