Update on G3 Terminal Vancouver
Construction of a modern and highly efficient Export Grain Terminal
at Lynnterm West Gate, North Vancouver
May 2017
Construction Update
Construction has been underway at our North Vancouver G3 Terminal Vancouver site at
Lynnterm West Gate since March 7, 2017, after we successfully completed an extensive
project and environmental review and permitting process with the Vancouver Fraser Port
Authority. Peter Kiewit Sons ULC has been selected as our design-build construction
contractor for the project. They have extensive experience and success building large scale
projects in British Columbia, including the Port Mann Bridge and the Sea to Sky Highway.
Going with the Grain
From March to present, our construction activities have included the demolition of old
buildings/structures, site clean-up, relocating underground utilities, digging foundations,
and dock panel removal (involving no in water works). We will manage dust on site using
water trucks and expect minimal traffic impacts in the non-industrial area during this time.
We will conduct most construction activities from Monday to Saturday between 7:00
am and 8:00 pm. If we need to conduct construction outside these hours we will require
authorization from the Vancouver Fraser Port Authority and we will notify you by email
ahead of any extended work hours.
What’s coming up - June to August
Industrial traffic requiring access to Lynnterm West Gate will be rerouted to a temporary
detour starting in June this year. The temporary detour will be on the east side of Lynn
Creek accessed via Mountain Highway, Dominion road and Harbour avenue, then
along a temporary road built over the rail line and bridge to the G3 and Vancouver
Pile Driving sites. We will monitor traffic and adjust to minimize traffic disruptions to
local businesses located in the industrial area. There will be a small and temporary
realignment of access to the Harbourview Dog Park and while we have made
considerable efforts to ensure a safe and timely route be maintained to the parking lot,
we suggest that dog owners may wish to access the park via the trail via access points
to the north. We apologize for the inconvenience and will be working quickly to install
the new roadway safely, and with as little impact as possible.
Industrial traffic detour illustrated by yellow line
Later this summer, we plan to begin marine and land pile work including pile driving
90 metres (300 ft.) south of the existing berth face to support up to three ship-loading
cranes. Noise levels generated on site will remain below the construction noise limits of Reducing
both the City of North Vancouver and the District of North Vancouver. To protect the construction traffic
marine environment, we will surround the pile removal area with containment booms, Since the start of
employ a bubble curtain during pile driving to reduce underwater sound levels, and
use biodegradable hydraulic fluid in marine machinery. The removal of creosote-treated construction, we have
piles will remove a contaminant of concern for aquatic life. barged 30,000 tonnes of
We will also begin concrete pours of the foundations for several buildings which will aggregate to site, which has
involve the erection of a crane and a few days of 24/7 pours as it is a necessity that reduced traffic impact by
the work is continuous. We will require authorization from the Vancouver Fraser Port 1,200 dump trucks.
Authority and will notify you by email ahead of any extended work hours.