Page 10 - BC Hydro’s Site C Project
P. 10

Site C to the rest of the BC Hydro system through       The need for foundation enhancements on the

        the Peace Canyon generating station.                    right bank, along with other cost pressures prior to

                                                                COVID-19, have also contributed to the increase. In
        The Site C Project continues to face significant        June 2020, the B.C. Treasury Board approved the

        challenges that have materially impacted the            new budget of $16 billion and the new in-service

        project cost and schedule. In February 2021, the        date of 2025.
        Government of British Columbia (B.C.) announced a

        revised cost estimate to complete the Project of $16    There are significant challenges relate to
        billion, along with a new expected in-service date of   geotechnical issues on the right bank. By early

        2025, as a result of the delays and impacts of the      2020, BC Hydro had determined that significant

        pandemic.                                               foundation enhancements were required to increase