Page 9 - BC Hydro’s Site C Project
P. 9

measures approx. 26 feet (8 m) wide and 17 (5 m)        the rear. In addition, there are three traffic control
        feet tall.                                              cars, three pilot cars and two supervisor cars

                                                                accompanying the shipment. It takes about a week          Photo Credit – BC Hydro

        The runners will leave by ship from the Port of         for the turbine runner to travel the approximately
        Santos, Brazil and it will take about six weeks for     1,150 kilometres from Prince Rupert to the project

        them to arrive at the Port of Prince Rupert. The        site southwest of Fort St. John.
        turbine runners are off loaded in Prince Rupert and

        trucked one at a time by road using a special truck     Q: Are there any other things you would like to

        and trailer unit that can handle the weight of the      highlight at this time?
        turbine. The trailer is 81 metres long x 7.98 metres    A: The Site C substation was placed into service and

        wide (267’ L x 26’ W). A convoy is made up of one       the first of two transmission lines was energized in
        truck in front of the trailer and two push trucks in    October 2020; these transmission lines connect