Page 6 - Hydro-Quebec Micoua-Saguenay Transmission Project
P. 6

Micoua-Saguenay transmission line construction site, in the city of Saint-Honoré in Saguenay – Lac-St-Jean, january 2022. (Photo Hydro-Québec)  Micoua-Saguenay transmission line construction site, in the Shipshaw sector of the city of Saguenay, August 2021. (Photo Hydro-Québec)

            Micoua-Saguenay line construction site, campement à Labrieville en HauteCôte-Nord, January 2021 (Photo Hydro-Québec)
                                                                                                                                                                                          worksites along the way, while keeping in mind
                                                                                                                                       Our teams are working hard to                      our number one priority which remains the health

                                                                                                                                     deliver this project and are proud
                                                                                                                                                                                          and safety of our workers and everyone around the
                                                                                                                                              to take part in such a
                                                                                                                                                                                          sites. There are 588 electric poles and each of them
                                                                                                                                                   big endeavor.                          is a separate construction site and this needs to be


                                                                                                                                                                                          done in a precise order.
                                                                                                                                   have resulted in increased power flow along the

                                                                                                                                   lines in the Manic–Québec corridor towards the         “Our teams are working hard to deliver this project

                                                                                                                                   major load centers, making the new line necessary.”    and are proud to take part in such a big endeavor,”

                                                                                                                                                                                          says Rousseau.
                                                                                                                                   All Hydro-Québec clients will benefit from this

                                                                                                                                   project as it aims to reenforce the transmission       The commissioning of the new line is scheduled for
                                                                                                                                   network’s reliability across the province. The main    2023.

                                                                                                                                   challenge in the realization of this project is in

                                                                                                                                   the length of the line. It is 262 kilometres long,            www.hydroquebec.com/projects/micoua-saguenay-line
                                                                                                                                   which means we need to manage many different


    6                                                                                                                                                                                                                                            7