Station in Swift Current, we awarded $140 million
        locally with over $10 million to Indigenous contracts,

        labour and subcontracts, and we are on track to

        significantly improve on those successes with Great
        Plains,” says Cherry.




        Burns & McDonnell, who have designed or
        constructed more than 70 natural gas power plants

        throughout North America were chosen for the

        engineering, procurement, and construction of the
        360-MW, combined cycle gas turbine (CCGT). Hiring

        local and indigenous companies and workers as                   Proud supplier for the
        sub-contractors and labor on the project has been             Saskpower Great  Plains

        prioritized.
                                                                              Power Station.
   (Photo Credit – SaskPower)  Positive economic benefits are anticipated for the   www.noramco.ca                   37






                                                                              MAY 2022  |  BUSINESS ELITE CANADA