S        askatoon’s water treatment system is


                                                                         getting an upgrade.



                                                                 This latest project’s origins go back to 2015,

                                                                 when Saskatoon Water completed the Avenue H

                                                                 Water Treatment Plant Pumphouse and Reservoir
                                                                 Expansion Project. The expansion boasted a

                                                                 reservoir expansion, an ultraviolet (UV) inactivation
                                                                 system, and new high lift distribution, but still

                                                                 needed a new transfer pumping facility to convey

                                                                 water from the clear wells through the UV reactors
                                                                 and into the Avenue H Reservoir to be pumped to

                                                                 the distribution system.

                                                                 That Transfer Pumping facility is now being built
                                                                 and will be operational in early 2024.




                                                                 The current Transfer Pumping and Electrical








                                                                              MAY 2022  |  BUSINESS ELITE CANADA     41