Page 3 - TransAqua WWTP Project
P. 3

By Tina Costanza                                        its new guidelines for their effluent regulations,
                                                                explains Kevin Rice, General Manager of TransAqua

            f there’s one thing the citizens of Dieppe,         and responsible for delivery of the Wastewater

            Moncton and Riverview are passionate about,         Treatment Facility Upgrade and Modernization
            it’s the Petitcodiac River that flows through       Project. TransAqua then had 10 years, to Dec. 31,

      Ithat tri-community in New Brunswick. It’s                2020, to meet the guidelines.

        where residents and visitors enjoy recreational
        activities, such as surfing the tidal bore, boating     The governments of Canada and New Brunswick

        and fishing. It’s also the destination of the flow from   pitched in to help. Each has contributed $22.6

        the TransAqua Wastewater Treatment Facility in          million to the $90.4-million project. TransAqua is
        Riverview.                                              providing the remaining funds.



        Clearly, it’s crucial the facility does its job well —   The improvements will also stabilize the wastewater

        clean water in the river supports tourism, protects     treatment rate and create pre- and post-

        public health, and ensures the river remains a          construction jobs. Sixty-five contractors have been
        source of recreation — and TransAqua has been           working at the site this past spring. The average

        upgrading and modernizing the facility.                 number of workers throughout the year ranges
                                                                between 40 and 60, depending on what’s going on

        The work stems from the CCME (the Canadian              at the time. Come July 2020, Rice says TransAqua

        Council of Ministers of the Environment) having         estimates about 100 contractors will be on-site for a
        deemed the facility in 2010 to be at high risk under    few months.