Page 7 - TransAqua WWTP Project
P. 7

Primary Clarifiers



        The upgrade and modernization project consists          access galleries to the bioreactor are complete.
        of five phases, and it’s now in phases 3, 4 and 5,      In the blower building, ventilation, duct and electrical

        specifically phase 3A, 3B, 3C and 4A. Phases 1          work in the basement are finished. The backup

        (preliminary treatment) and 2 (primary treatment)       power generators and five blowers are in place,
        are complete.  Phase 3A consists of the bioreactor,     ready for electrical and mechanical connections.

        phase 3B is the blower building, phase 3C is the
        secondary clarifier, phase 4A is solid handling,        Other work that has been done includes the

        phase 4B is the biosolids load-out facility, phase 4C   expansion of the secondary clarifier electrical

        is the bio filter, and phase 5 is UV disinfection.      building, the relocation of a water main, the
                                                                construction of secondary clarifier 4 and three

        Rice provided a rundown of the work that has been       sludge tanks, equipment replacement in secondary

        completed to date.                                      clarifiers 1, 2 and 3, the installation of the HVAC
                                                                system, two rotary drum thickeners, the polymer

        In terms of the bioreactor, 21 of 36 walls are          system, domestic water system and piping, and

        complete. The slab, service tunnel, effluent supply     the mechanical upgrading of three 30-year-old
        channel and return channel, and the north and south     centrifuges.