Major Milestone Darlington Refurbishment (Photo Credit – OPG)


        turbine generators and fuel handling equipment;         requires removing fuel and heavy water, and

        improve systems; and complete plant upgrades to         isolating the unit from the rest of the station in a

        meet regulatory requirements.                           process known as islanding.



        About 480 pressure tubes and calandria tubes, and       The next step is disassembling the reactor, which

        960 feeder pipes for each reactor will be removed       includes removing, storing or replacing thousands
        and replaced as part of the project.                    of components with specialized tools that workers

                                                                operate by remote control. Reassembling the unit

        But first, before disassembling a reactor, workers      requires just as much precision to inspect, clean and
        must disconnect it from the power grid. This            install the components.