Page 13 - Darlington Refurbishment Project
P. 13

the unit begins to warm up. Workers restore

                                                                containment and then begin reconnecting the unit
                                                                to the rest of the operating station. The goal now is

                                                                for the unit to achieve criticality, OPG explained.
                                                                After final high power testing, control room

                                                                operators gradually raise the unit to full-power

                                                                operation.



                                                                The project has remained on budget and on

                                                                schedule, OPG has reported, despite the COVID-19
                                                                pandemic.




                                                                Refurbishment of Unit 1 has been scheduled to
                                                                start in the second quarter of 2022, and is expected

                                                                to be finished in the second quarter of 2025.
                                                                Refurbishment of Unit 4 is to begin in the fourth

                                                                quarter of 2023, with completion set for the fourth

                                                                quarter of 2026.



                                                                The refurbishment of Unit 2 was ahead of schedule
                                                                to meet the revised completion date in May.

                                                                More than 99 per cent of Unit 2 work has been

                                                                completed as of mid-May, and 58 of 58 systems
                                                                have been returned to service. OPG declared
        The last step is powering up the unit by following      construction complete on Unit 2 in March, following

        several step-by-step approvals. These confirm the       the successful restoration of the airlocks and vault

        quality of the work and ensure that staff, equipment    containment pressure tests.
        systems and operating procedures are ready for

        the start-up process. Workers, meanwhile, refill        Prior to the pandemic, the team was on track to

        the moderator with heavy water, load fuel into the      begin Unit 3’s refurbishment in April. OPG has now
        fuel assemblies in the reactor core, and fill and       decided to keep Unit 3 running to ensure a stable

        pressurize the heat transport system.                   supply of clean electricity for Ontario, and to defer

                                                                the start of its refurbishment to the third quarter of
        Then the nuclear fission process is started and         2020.