will run approximately 14.5 kilometres from
the Lakeview Water Treatment Plant on Lake
Ontario to the Hanlan Reservoir. It is also in-
stalling a 1,500-mm Mississauga City Centre
Subtransmission Main that will run approxi-
mately six kilometres from the Hanlan Reser-
voir and Pumping Station to the intersection
of Cawthra and Burnhamthorpe Roads. “We
have a York-Peel servicing agreement which
means we must supply water to the Region of
York and the Hanlan Water Project will be able
to supply that water as well,” said Turner.
The massive $450 million project consists of
three active construction phases -- contracts
1, 2 & 3 – all of which are under construction