Digester Tank Construction





















































        Mike Sadowski, Wastewater Plant Manager.                plant is now able to capture the biogas produced

                                                                from the digester tanks and turn it into a renewable

        The primary objective of the project was to address     energy source where it can be run through the plant
        the capacity concerns associated with the digester      boiler system instead of using natural gas,” says

        process area. Adding a fourth digester tank provided    Lacny.

        the plant additional capacity and because the
        digester process area is linked to the plant heating    Finally, the project upgraded the existing biogas

        system, there was a great opportunity to improve        flare system to now include two enclosed flare

        the heating system for the entire plant.                stacks which allows for excess biogas to be
                                                                efficiently flared off to the atmosphere.

        The project also addressed the concern surrounding
        the excess biogas that was already being produced       “With this being the only wastewater treatment

        at the plant. “After completing this upgrade, the       plant for the City of Saskatoon, all citizens will