Page 73 - BEC / OCT / 2022
P. 73

Digester Tank Complete


















































                                                                                                   Biotrickling Filter Complete

        benefit from the upgrades of this project as this       commissioning the actual system that was installed

        project ensures that the City of Saskatoon can          while still operating and maintaining the other areas

        continue to maintain wastewater processing              of the plant. Other major groups to thank include
        standards that protect our environment,” says           the City project team, the construction contractor

        Kelsea Doll, Project Manager. “With the ability to      team from Graham Construction, and the design

        utilize biogas for heating, this project has also       consultant team from Jacobs.”
        reduced the City’s overall natural gas consumption.”

                                                                With the addition of a fourth digester tank, it is

        “The City of Saskatoon Wastewater Treatment             anticipated that the Wastewater Treatment Plant will
        Plant staff were very supportive throughout the         not require a digester capacity increase for another

        entire project,” Doll adds. “Staff participated in      30 years though this projection is dependent
        performing design reviews, accommodating the            on population growth and operating permit

        contractor on the plant site during construction, and   requirements set out by the WSA.


                                                                              OCT 2022  |  BUSINESS ELITE CANADA     73
   68   69   70   71   72   73   74   75   76   77   78