Digester Tank Complete
Biotrickling Filter Complete
benefit from the upgrades of this project as this commissioning the actual system that was installed
project ensures that the City of Saskatoon can while still operating and maintaining the other areas
continue to maintain wastewater processing of the plant. Other major groups to thank include
standards that protect our environment,” says the City project team, the construction contractor
Kelsea Doll, Project Manager. “With the ability to team from Graham Construction, and the design
utilize biogas for heating, this project has also consultant team from Jacobs.”
reduced the City’s overall natural gas consumption.”
With the addition of a fourth digester tank, it is
“The City of Saskatoon Wastewater Treatment anticipated that the Wastewater Treatment Plant will
Plant staff were very supportive throughout the not require a digester capacity increase for another
entire project,” Doll adds. “Staff participated in 30 years though this projection is dependent
performing design reviews, accommodating the on population growth and operating permit
contractor on the plant site during construction, and requirements set out by the WSA.